Cal-ISO, SRP sign agreement for SRP to participate in western EIM

Save It Saved

The California ISO (Cal-ISO) on April 27 said that it and Salt River Project (SRP) have signed an agreement for SRP to participate in the western Energy Imbalance Market (EIM) beginning in April 2020.

It is estimated that SRP – a community-based, not-for-profit public power utility, and the largest electricity provider in the greater Phoenix area – can save up to $4.5m annually by participating in the EIM, the Cal-ISO said.

The western EIM’s advanced market systems automatically find the lowest-cost energy to serve real-time consumer demands of participating utilities, the Cal-ISO said. That market enables utilities to buy and sell power more efficiently in the hour before the energy is needed, with five-minute plant dispatching, which result in improved efficiencies and cost savings, the Cal-ISO said.

According to the implementation agreement with SRP, which the Cal-ISO said it will file with FERC, SRP is to pay the Cal-ISO a fixed fee of $910,000 for costs incurred by the Cal-ISO to configure its systems to incorporate SRP into the EIM, subject to completion of certain milestones.

Current western EIM participants have realized savings totaling nearly $142m since the wholesale market was launched in November 2014, the Cal-ISO said in its statement, adding that utilities now active in the western EIM include PacifiCorp, NV Energy, Puget Sound Energy, and Arizona Public Service.

Other utilities that have formally agreed to join the EIM include Portland General Electric beginning on Oct. 1; Idaho Power on April 1, 2018; as well as Seattle City Light and Balancing Area of Northern California/Sacramento Municipal Utility District on April 1, 2019, the Cal-ISO said.

In a letter order that is dated March 14 and posted on the Cal-ISO’s website, FERC accepted the EIM implementation agreement involving Seattle City Light.

As noted in that letter order, the Cal-ISO in late January submitted the implementation agreement with The City of Seattle, by and through its City Light Department (Seattle City Light), setting forth the terms under which the Cal-ISO will extend its real-time energy market systems to provide imbalance energy service to Seattle City Light under the Cal-ISO’s EIM tariff provisions.

According to that implementation agreement, Seattle City Light will pay a fixed implementation fee of $310,000, subject to completion of six milestones, for recovery of the portion of the costs attributable to the Cal-ISO’s effort to configure its real-time market systems and incorporate Seattle City Light into the EIM.

FERC’s letter order said, “The implementation agreement is accepted for filing, effective April 1, 2017, as requested.”

Read the full article on TransmissionHub

About TransmissionHub (note you must have an account on TransmissionHub to access the full archive of intelligence articles, supporting documents and detailed project profiles)